In October 2021 Griffith’s were employed by Cormac Solutions Ltd. (CSL), part of the Corserv Group of companies owned and operated by Cornwall Council, as a specialist Contractor to undertake Rock Stabilisation works at Charlestown Harbour.
The South West Coastal Path (SWCP) runs through Charlestown and out towards Par to the East where the footpath runs along the crest of the sea cliffs. The failure of the sea wall and subsequent coastal erosion during storm events had undermined the SWCP, resulting in the temporary narrowing of the path. Cornwall Council were concerned that further erosion would see the complete loss of the path and a risk to the residential buildings at the crest. A design was precured by CSL which required the installation of 15No. soil nails to stabilise the upper section of the cliff and 53No. rock pins to hold the reinforced sprayed concrete facing. Weepholes were installed as required by the Designer.
To complete the works on the rock face access to the beach was required. Due to the distance of travel to bring a barge with an excavator, drilling rig, MEWP and all materials it was considered impractical. A barge would also limit the ability to safely clear the beach in the event of a storm. Griffith’s therefore chose to undertake a contract lift to bring plant and materials on and off the beach at the appropriate point in the construction sequence.